What the NOPSEMA Environment Plan register shows for the 183 plans it classifies as development: how many are filed, what happens to them, and the elapsed time from submission to decision, on two windows that both clear the reporting floor.

Measures
Elapsed time from submission to decision, from the public register
Basis
The NOPSEMA public register, frozen as a census table on 27 July 2026
Document
KLA-PINTEL-REP-005 Rev B, issued 22 October 2026
Cost
Your email address. No list, no follow-up sequence, no card.
Get the brief

One address, and the PDF is yours.

We ask for an email so we know who is reading it. That is the entire use of it.

  • No mailing list and no drip sequence
  • No third-party marketing tool — it arrives as an email to a person here
  • The download starts immediately
  • Would rather not? Write to services@klarite.com.au and we will send it back by hand.

Download the brief

PDF, KLA-PINTEL-REP-005 Rev B.

Or email services@klarite.com.au directly. We do not add anyone to a mailing list, and we do not run a follow-up sequence.

Klarite Pty Ltd uses what you enter here only to send you what you asked for and to reply. Some of our providers hold it outside Australia. See our privacy policy.

What the brief establishes

The findings, each with its population and n.

From the brief's own start-here page. Every duration is elapsed time from submission to decision for accepted plans, grouped by the year they were decided. The register cannot divide that time between the regulator and the titleholder, and the brief does not try.

01  Elapsed time for accepted development plans rose

A median of 75 days from submission to decision for plans decided 2017 to 2020 (n=38), and 239 days for plans decided 2023 to 2025 (n=32). Removing any one recent plan moves the recent median to between 229 and 249 days.

02  The rise holds when the windows move

Plans decided 2022 to 2025 had a median of 229 days (n=35), and plans decided 2021 to 2025 217 days (n=44).

03  Filings fell, but development held its share

72 development-stage plans were submitted in 2012 to 2014 and 27 in 2023 to 2025: 27.0% of all filings in the first period and 29.0% in the second. The brief does not say why.

04  New plans clear the floor

New development plans went from a median of 78 days (n=28, decided 2017 to 2020) to 217 days (n=24, decided 2023 to 2025). Revisions and each activity type are below the floor and are not shown.

05  Cancellation and refusal are uncommon

10 of 183 development-stage plans were cancelled (5.5%). 2 of the 168 with a completed decision were refused, both decided in 2012 or 2013. The register does not record why.

Read the size of the rise as a range

The brief puts a resampling interval of about 2.0 to 4.9 times on the 2023 to 2025 median (n=32) against the 2017 to 2020 median (n=38) (95%, bootstrap). The direction is clear; the size is not.

The population

What the brief is computed on.

From the brief's start-here page and its source note
FactValue
Development-stage plans183: 140 new plans and 43 revisions
Duration basisAccepted plans, including those accepted with conditions, grouped by decision year; 2026 excluded from the windows the brief leads with
Reporting floorAn elapsed-time median is led with only when it rests on at least 20 plans
RegisterCoverage to 17 July 2026; extracted 21 July 2026; frozen as a census table on 27 July 2026
By design

What this brief deliberately does not do.

No cause

It measures that elapsed time changed. It does not say why, and attributes no change to the regulator, to titleholders or to anyone else.

No forecast

No future volume, no future timeframe and no decision date for any plan is projected from this data.

No titleholder named

Like the Census, the brief names no titleholder and makes no cross-operator comparison.

Environment Plans only

No safety cases or other submissions, and no Environment Plan text is reproduced.

Read with it

The other briefs, and the Census.

ProveINTEL, Development and the Approval Clock. KLA-PINTEL-REP-005 Rev B. ProveINTEL is Klarite's tool for analysing the NOPSEMA public register of Environment Plans. Data derived from the public register at info.nopsema.gov.au. ProveINTEL is not affiliated with, or endorsed by, NOPSEMA.